The Construction Project of Highway No. Highway 1021 Dok Khamtai (Section 1), Phayao
Date of Commencement:
July 26, 2025
Date of Completion:
August 14, 2027
Contract No.:
สท.1/18/2568 Dated July 25, 2025
Contract Sum (Baht):
649,775,130.00
Client:
Department of Highways
Designed by:
Department of Highways
Constructed by:
Christiani & Nielsen (Thai) PCL
Location:
Highway Route No. 1021 between km. No.12+000.000 to km No.22+500.000. Dok Khamtai District, Phayao. The distance is approximately 10.500 km.
Project Coordinates:
19.178922 N, 100.012364 E